PK0-003 · Question #70

A project manager has been asked by a major stakeholder to modify the scope of a project in progress. Which of the following is the best FIRST step?

The correct answer is A. Assess the impact the change will have on the project.. When a stakeholder requests a change to a project's scope, the immediate first step for a project manager is to assess the potential impact of that change on all project constraints. This assessment helps inform subsequent decisions and approvals regarding the change.

Project management concepts

Question

A project manager has been asked by a major stakeholder to modify the scope of a project in progress. Which of the following is the best FIRST step?

Options

  • AAssess the impact the change will have on the project.
  • BCall a meeting and ensure all stakeholders agree to the changes.
  • CSubmit a change request to the PMO.
  • DObtain written approval from the project sponsor and make the requested changes.

How the community answered

(22 responses)
  • A
    73% (16)
  • B
    9% (2)
  • C
    14% (3)
  • D
    5% (1)

Why each option

When a stakeholder requests a change to a project's scope, the immediate first step for a project manager is to assess the potential impact of that change on all project constraints. This assessment helps inform subsequent decisions and approvals regarding the change.

AAssess the impact the change will have on the project.Correct

The best first step when a scope change is requested is to assess its impact on the project's schedule, cost, quality, resources, and risks. This initial analysis provides the necessary information for the project manager and other stakeholders to make informed decisions about whether to proceed with the change.

BCall a meeting and ensure all stakeholders agree to the changes.

Calling a meeting to seek agreement prematurely, before understanding the change's impact, is inefficient and may lead to ill-informed decisions.

CSubmit a change request to the PMO.

Submitting a change request to the PMO or change control board should happen after the impact assessment, as the request needs to include details about the change's implications.

DObtain written approval from the project sponsor and make the requested changes.

Obtaining written approval and making changes without first assessing the impact bypasses a critical step in change control and can lead to unforeseen negative consequences for the project.

Concept tested: Project change management process - first step

Source: https://learn.microsoft.com/en-us/project/what-is-change-management