CompTIA
PK0-003 · Question #425
PK0-003 Question #425: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-003 to reveal the answer and full explanation for question #425. The question stem and answer options stay visible for context.
Question
A project manager is using a vendor with a fixed bid contract. The vendor would like to help out with other parts of the project. Which of the following should the project manager do NEXT?
Options
- AReview the vendors SOW and determine if the additional work items can be included.
- BAllow the vendor to accept the additional work on a time and material (T&M) basis.
- CAllow the vendor to accept the additional work, but honor the fixed bid price.
- DExplain to the vendor that the work is already assigned to the vendor with the lowest cost.
Unlock PK0-003 to see the answer
You've previewed enough free PK0-003 questions. Unlock PK0-003 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.