In the scope statement it is mentioned there is a strong possibility of a hurricane impacting the schedule at any given time. This notation would be considered a(n):

The correct answer is D. Risk. A strong possibility of a hurricane impacting the schedule describes an uncertain future event that could affect project objectives, which is the definition of a risk.

Project management concepts

Question

In the scope statement it is mentioned there is a strong possibility of a hurricane impacting the schedule at any given time. This notation would be considered a(n):

Options

  • AAssumption
  • BIssue
  • CConstraint
  • DRisk

How the community answered

(48 responses)
  • A
    4% (2)
  • B
    6% (3)
  • C
    2% (1)
  • D
    88% (42)

Why each option

A strong possibility of a hurricane impacting the schedule describes an uncertain future event that could affect project objectives, which is the definition of a risk.

AAssumption

An assumption is a factor in planning that is considered to be true, real, or certain without proof, not an uncertain event.

BIssue

An issue is a problem or concern that is already happening or has happened, requiring immediate attention, unlike a potential future event.

CConstraint

A constraint is a limiting factor or restriction that affects the execution of the project, such as budget or time, not an uncertain event that might impact the schedule.

DRiskCorrect

A risk is an uncertain event or condition that, if it occurs, will have a positive or negative effect on one or more project objectives, such as schedule. The potential for a hurricane to impact the schedule is a classic example of a project risk.

Concept tested: Project risk identification