PK0-003 · Question #254
In the scope statement it is mentioned there is a strong possibility of a hurricane impacting the schedule at any given time. This notation would be considered a(n):
The correct answer is D. Risk. A strong possibility of a hurricane impacting the schedule describes an uncertain future event that could affect project objectives, which is the definition of a risk.
Question
In the scope statement it is mentioned there is a strong possibility of a hurricane impacting the schedule at any given time. This notation would be considered a(n):
Options
- AAssumption
- BIssue
- CConstraint
- DRisk
How the community answered
(48 responses)- A4% (2)
- B6% (3)
- C2% (1)
- D88% (42)
Why each option
A strong possibility of a hurricane impacting the schedule describes an uncertain future event that could affect project objectives, which is the definition of a risk.
An assumption is a factor in planning that is considered to be true, real, or certain without proof, not an uncertain event.
An issue is a problem or concern that is already happening or has happened, requiring immediate attention, unlike a potential future event.
A constraint is a limiting factor or restriction that affects the execution of the project, such as budget or time, not an uncertain event that might impact the schedule.
A risk is an uncertain event or condition that, if it occurs, will have a positive or negative effect on one or more project objectives, such as schedule. The potential for a hurricane to impact the schedule is a classic example of a project risk.
Concept tested: Project risk identification