nerdexam
ExamsPK0-003Questions#188
CompTIA

PK0-003 · Question #188

PK0-003 Question #188: Real Exam Question with Answer & Explanation

The correct answer is D: 1.5. See the full explanation below for the reasoning.

Question

The project has spent $5,000 to date. The earned value of the project is $7,500. Which of the following is the project's CPI?

Options

  • A-$2,500
  • B$12,500
  • C0.67
  • D1.5

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice