CompTIA
PK0-003 · Question #188
PK0-003 Question #188: Real Exam Question with Answer & Explanation
The correct answer is D: 1.5. See the full explanation below for the reasoning.
Question
The project has spent $5,000 to date. The earned value of the project is $7,500. Which of the following is the project's CPI?
Options
- A-$2,500
- B$12,500
- C0.67
- D1.5
Community Discussion
No community discussion yet for this question.