nerdexam
CompTIA

PK0-003 · Question #182

A project manager has calculated their project to have a SV of -$5,000. Which of the following conclusions is correct?

The correct answer is C. The project is behind schedule. This question assesses the understanding of Schedule Variance (SV) in Earned Value Management (EVM) and how to interpret a negative value.

Project management concepts

Question

A project manager has calculated their project to have a SV of -$5,000. Which of the following conclusions is correct?

Options

  • AThe project is over budget
  • BThe project baseline is incorrect
  • CThe project is behind schedule
  • DThe project is under budget

How the community answered

(19 responses)
  • A
    5% (1)
  • B
    16% (3)
  • C
    79% (15)

Why each option

This question assesses the understanding of Schedule Variance (SV) in Earned Value Management (EVM) and how to interpret a negative value.

AThe project is over budget

Being over budget is indicated by a negative Cost Variance (CV = EV - AC), not Schedule Variance (SV).

BThe project baseline is incorrect

A negative SV indicates a deviation from the schedule baseline, but it does not imply the baseline itself is incorrect; rather, it shows performance is lagging against that baseline.

CThe project is behind scheduleCorrect

Schedule Variance (SV) is calculated as Earned Value (EV) minus Planned Value (PV). A negative SV (SV < 0), such as -$5,000, indicates that less work has been completed than planned for the current point in time, meaning the project is behind schedule.

DThe project is under budget

Being under budget is indicated by a positive Cost Variance (CV > 0), not Schedule Variance (SV).

Concept tested: Earned Value Management - Schedule Variance interpretation

Source: https://www.pmi.org/learning/library/earned-value-management-calculation-analysis-8215

Topics

#Earned Value Management (EVM)#Schedule Variance (SV)#Project schedule

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice