nerdexam
CompTIA

PK0-003 · Question #130

A new project manager is beginning work on a high profile project with a budget of $3.2 million. The project manager has not spoken directly to the IT department regarding the necessary hardware for t

The correct answer is D. Assumptions. The project manager is making a decision about necessary hardware based on prior experience without direct verification, which exemplifies an assumption in project management.

Project management concepts

Question

A new project manager is beginning work on a high profile project with a budget of $3.2 million. The project manager has not spoken directly to the IT department regarding the necessary hardware for this project. The project manager has determined, based on past experience, that it will not be necessary to purchase additional servers for the project. This is an example of which of the following?

Options

  • AConstraints
  • BStandards compliance
  • CAcceptance criteria
  • DAssumptions

How the community answered

(23 responses)
  • A
    13% (3)
  • B
    4% (1)
  • C
    4% (1)
  • D
    78% (18)

Why each option

The project manager is making a decision about necessary hardware based on prior experience without direct verification, which exemplifies an assumption in project management.

AConstraints

Constraints are limiting factors or conditions that affect the project, such as budget, schedule, or resources.

BStandards compliance

Standards compliance refers to adhering to established rules, guidelines, or specifications, not a belief about resource availability.

CAcceptance criteria

Acceptance criteria are the conditions that must be met for a deliverable to be considered acceptable by stakeholders.

DAssumptionsCorrect

An assumption is a factor that is considered to be true, real, or certain for planning purposes, without proof or demonstration. In this scenario, the project manager assumes that existing servers are sufficient based on past experience, without consulting the IT department for current project needs.

Concept tested: Project assumptions identification

Topics

#Assumptions#Project planning#Risk identification

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice