PK0-003 · Question #109

The project team is not comfortable moving an expensive material. A third party is hired to move the material. This is an example of risk:

The correct answer is A. Transference. Hiring a third party to handle a risky task, thereby shifting the responsibility and potential impact of the risk to them, is an example of risk transference.

Project management concepts

Question

The project team is not comfortable moving an expensive material. A third party is hired to move the material. This is an example of risk:

Options

  • ATransference
  • BSharing
  • CAvoidance
  • DAcceptance

How the community answered

(35 responses)
  • A
    74% (26)
  • B
    3% (1)
  • C
    14% (5)
  • D
    9% (3)

Why each option

Hiring a third party to handle a risky task, thereby shifting the responsibility and potential impact of the risk to them, is an example of risk transference.

ATransferenceCorrect

Risk transference involves shifting the responsibility and impact of a risk to a third party, often through contracts, insurance, or outsourcing. By hiring an external party to move the material, the project transfers the risk associated with that specific activity.

BSharing

Risk sharing involves multiple parties taking on a portion of the risk, which is not what happened when a single third party was hired to take full responsibility for the task.

CAvoidance

Risk avoidance means eliminating the threat entirely by changing the project plan or scope, not delegating the task to another entity.

DAcceptance

Risk acceptance means acknowledging the risk and deciding not to take any action, which is contrary to hiring a third party to manage it.

Concept tested: Risk response strategies - transference

Source: https://www.pmi.org/learning/library/risk-management-response-strategies-9243

Topics

#risk management#risk transference#risk response strategies

Community Discussion

No community discussion yet for this question.