PGMP · Question #81

You need to create a document that will define the costs, resources, and characteristics of each deliverable the program will create. What document should you create?

The correct answer is B. Program work breakdown structure dictionary. The Program Work Breakdown Structure (WBS) Dictionary is the document that provides detailed descriptions of each component in the WBS, including costs, resources, technical characteristics, and other defining information for each deliverable. The WBS itself (A) is just a…

Program Life Cycle Management

Question

You need to create a document that will define the costs, resources, and characteristics of each deliverable the program will create. What document should you create?

Options

  • AProgram work breakdown structure
  • BProgram work breakdown structure dictionary
  • CProgram charter
  • DProgram scope statement

How the community answered

(51 responses)
  • A
    2% (1)
  • B
    90% (46)
  • C
    6% (3)
  • D
    2% (1)

Explanation

The Program Work Breakdown Structure (WBS) Dictionary is the document that provides detailed descriptions of each component in the WBS, including costs, resources, technical characteristics, and other defining information for each deliverable. The WBS itself (A) is just a hierarchical decomposition of deliverables without those details. The program charter (C) authorizes the program, and the scope statement (D) describes what is and isn't in scope - neither defines per-deliverable cost and resource details.

Topics

#WBS Dictionary#Program Scope Management#Program Deliverables#Program Planning