PGMP · Question #67

Which one of the following is not an output of the direct and manage program execution process?

The correct answer is B. Program budget. The program budget is an INPUT to the direct and manage program execution process - it is already established before execution begins and is used to guide and fund the work. Outputs of this process include deliverables and results of program work, change requests (issues or…

Program Life Cycle Management

Question

Which one of the following is not an output of the direct and manage program execution process?

Options

  • AResults of program work
  • BProgram budget
  • CChange requests
  • DRequest to terminate the program

How the community answered

(18 responses)
  • B
    89% (16)
  • C
    6% (1)
  • D
    6% (1)

Explanation

The program budget is an INPUT to the direct and manage program execution process - it is already established before execution begins and is used to guide and fund the work. Outputs of this process include deliverables and results of program work, change requests (issues or needs that arise during execution), and requests to terminate the program (if conditions warrant). The budget itself is not created by executing the program; it is consumed and tracked during execution.

Topics

#Program Execution#Program Life Cycle Management#Process Outputs#Direct and Manage Program Execution