You are the program manager for your organization. As your program is being initiated there is some initial concern from the management about the utilization of resources in your program and the…

The correct answer is A. Resource leveling heuristic. A resource leveling heuristic is a rule or constraint applied to manage resource allocation - such as capping the hours a resource can contribute to a program within a given time period. In this case, management's 20-hour-per-week cap is exactly such a heuristic, used to…

Program Life Cycle Management

Question

You are the program manager for your organization. As your program is being initiated there is some initial concern from the management about the utilization of resources in your program and the need for resources in their day-to-day roles in operations. Management has set a limit on your program that resources may only work 20 hours per week on the program. What is this limit of resource hours in a time period known as?

Options

  • AResource leveling heuristic
  • BResource requirements
  • CProgram risk
  • DResource utilization

How the community answered

(30 responses)
  • A
    87% (26)
  • B
    7% (2)
  • C
    3% (1)
  • D
    3% (1)

Explanation

A resource leveling heuristic is a rule or constraint applied to manage resource allocation - such as capping the hours a resource can contribute to a program within a given time period. In this case, management's 20-hour-per-week cap is exactly such a heuristic, used to balance program demands against operational needs. Resource requirements refer to the types and quantities of resources needed. Resource utilization describes how efficiently resources are being used. Program risk is unrelated to this scheduling/allocation concept.

Topics

#Resource Management#Resource Leveling#Program Constraints#Program Planning