nerdexam
PMI

PGMP · Question #561

When should a program manager approve the closure of a component project?

The correct answer is C. When program deliverables are complete. A component project exists to contribute to program-level deliverables, not to stand alone. The program manager approves component closure when the program deliverables - those that the component was established to produce - are complete and accepted. This distinction is…

Program Life Cycle Management

Question

When should a program manager approve the closure of a component project?

Options

  • AWhen acceptance criteria of the project are met
  • BWhen the project has delivered the project benefits
  • CWhen program deliverables are complete
  • DWhen project deliverables are complete

How the community answered

(19 responses)
  • A
    5% (1)
  • B
    11% (2)
  • C
    79% (15)
  • D
    5% (1)

Explanation

A component project exists to contribute to program-level deliverables, not to stand alone. The program manager approves component closure when the program deliverables - those that the component was established to produce - are complete and accepted. This distinction is critical: a component project may finish its own internal deliverables (option D) while integration into the broader program deliverable is still incomplete. Closing based solely on project-level acceptance (A) or project benefits (B) misses the program manager's broader perspective. Only when the component's contributions have fully materialized as program-level outcomes is closure appropriate from a program governance standpoint.

Topics

#Program Closure#Component Project Management#Program Manager Role#Program Deliverables

Community Discussion

No community discussion yet for this question.

Full PGMP Practice