PGMP · Question #561
When should a program manager approve the closure of a component project?
The correct answer is C. When program deliverables are complete. A component project exists to contribute to program-level deliverables, not to stand alone. The program manager approves component closure when the program deliverables - those that the component was established to produce - are complete and accepted. This distinction is…
Question
When should a program manager approve the closure of a component project?
Options
- AWhen acceptance criteria of the project are met
- BWhen the project has delivered the project benefits
- CWhen program deliverables are complete
- DWhen project deliverables are complete
How the community answered
(19 responses)- A5% (1)
- B11% (2)
- C79% (15)
- D5% (1)
Explanation
A component project exists to contribute to program-level deliverables, not to stand alone. The program manager approves component closure when the program deliverables - those that the component was established to produce - are complete and accepted. This distinction is critical: a component project may finish its own internal deliverables (option D) while integration into the broader program deliverable is still incomplete. Closing based solely on project-level acceptance (A) or project benefits (B) misses the program manager's broader perspective. Only when the component's contributions have fully materialized as program-level outcomes is closure appropriate from a program governance standpoint.
Topics
Community Discussion
No community discussion yet for this question.