nerdexam
PMI

PGMP · Question #537

A component is scheduled to close at the end of the week. What should the program manager verify prior to allowing the component to close?

The correct answer is B. The component has met the quality requirements to meet program objectives. Before a program component can be formally closed, the program manager must verify that the component's outputs meet the defined quality requirements (B), as quality is the primary criterion that determines whether the deliverables are fit for purpose and can contribute to the…

Program Life Cycle Management

Question

A component is scheduled to close at the end of the week. What should the program manager verify prior to allowing the component to close?

Options

  • AThe component has released resources to meet program objectives
  • BThe component has met the quality requirements to meet program objectives
  • CThe component has met the schedule requirements to meet program objectives
  • DThe component has met the benefits realization criteria to meet program objectives

How the community answered

(41 responses)
  • A
    7% (3)
  • B
    85% (35)
  • C
    2% (1)
  • D
    5% (2)

Explanation

Before a program component can be formally closed, the program manager must verify that the component's outputs meet the defined quality requirements (B), as quality is the primary criterion that determines whether the deliverables are fit for purpose and can contribute to the program's benefit realization. While schedule adherence (C) and resource release (A) are also closure considerations, they do not override quality. Benefits realization criteria (D) are typically assessed at the program level over time, not solely at component closure. A component that finishes on time but with substandard quality could undermine the entire program's objectives.

Topics

#Program Closure#Component Management#Quality Requirements#Program Lifecycle

Community Discussion

No community discussion yet for this question.

Full PGMP Practice