PGMP · Question #50
PGMP Question #50: Real Exam Question with Answer & Explanation
The correct answer is C: Integration management. See the full explanation below for the reasoning.
Program Life Cycle Management
Question
A knowledge area defines a subset of program management and its processes within that domain. For example, the knowledge area of quality management includes the processes related directly to quality management only. Which knowledge area ensures that all knowledge areas interact correctly with one another?
Options
- AProgram benefits management
- BProgram management planning
- CIntegration management
- DCommunications management
Topics
#Program management knowledge areas#Integration management#Program management fundamentals#Program structure