PGMP · Question #344
The team has an approved charter and has started planning, determining potential risks that could occur on the project. Which of the following best describe project risk?
The correct answer is C. It can be either a negative or positive event. Per the PMBOK Guide, a project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives. Negative risks are called threats; positive risks are called opportunities. Risk management addresses both. Option A and B are…
Question
The team has an approved charter and has started planning, determining potential risks that could occur on the project. Which of the following best describe project risk?
Options
- AIt can be a negative event only
- BIt can be a positive event only
- CIt can be either a negative or positive event
- DIt can be something that has already happened
How the community answered
(39 responses)- A3% (1)
- B3% (1)
- C90% (35)
- D5% (2)
Explanation
Per the PMBOK Guide, a project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives. Negative risks are called threats; positive risks are called opportunities. Risk management addresses both. Option A and B are incomplete. Option D is incorrect because risk is future-oriented - once an event has already happened, it is an issue, not a risk.
Topics
Community Discussion
No community discussion yet for this question.