PGMP · Question #243

You are the program manager of the NHQ Program for your organization. Your program is nearing the completion of one of its major phases and there are several resources that should be released at this

The correct answer is B. Transition plan. The transition plan specifically governs the release of program resources and the formal transfer of deliverables and benefits to operational units at phase or program closure.

Program Life Cycle Management

Question

You are the program manager of the NHQ Program for your organization. Your program is nearing the completion of one of its major phases and there are several resources that should be released at this time. What program management plan will guide you to release of the program resources and transfer the resources and benefits to operations within the organization?

Options

  • AResource management plan
  • BTransition plan
  • CCommunications management plan
  • DBenefits management plan

How the community answered

(34 responses)
  • A
    12% (4)
  • B
    79% (27)
  • C
    3% (1)
  • D
    6% (2)

Why each option

The transition plan specifically governs the release of program resources and the formal transfer of deliverables and benefits to operational units at phase or program closure.

AResource management plan

The resource management plan governs how resources are acquired, developed, and managed during the program but does not direct their formal release or transfer to operations.

BTransition planCorrect

The transition plan defines the activities, responsibilities, and timing required to hand over program deliverables, capabilities, and resources to the receiving operational organization. It ensures operational readiness and documents how resources are released and benefits are sustained after the program or phase concludes, directly matching the described scenario.

CCommunications management plan

The communications management plan defines how information flows to stakeholders but has no function in directing resource release or operational handover.

DBenefits management plan

The benefits management plan tracks benefit realization over time but does not contain the operational transfer procedures for resources and deliverables.

Concept tested: Program transition planning and resource release to operations

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-program-management

Topics

#Transition Management#Program Closure#Resource Release#Benefit Realization