PGMP · Question #243
You are the program manager of the NHQ Program for your organization. Your program is nearing the completion of one of its major phases and there are several resources that should be released at this
The correct answer is B. Transition plan. The transition plan specifically governs the release of program resources and the formal transfer of deliverables and benefits to operational units at phase or program closure.
Question
You are the program manager of the NHQ Program for your organization. Your program is nearing the completion of one of its major phases and there are several resources that should be released at this time. What program management plan will guide you to release of the program resources and transfer the resources and benefits to operations within the organization?
Options
- AResource management plan
- BTransition plan
- CCommunications management plan
- DBenefits management plan
How the community answered
(34 responses)- A12% (4)
- B79% (27)
- C3% (1)
- D6% (2)
Why each option
The transition plan specifically governs the release of program resources and the formal transfer of deliverables and benefits to operational units at phase or program closure.
The resource management plan governs how resources are acquired, developed, and managed during the program but does not direct their formal release or transfer to operations.
The transition plan defines the activities, responsibilities, and timing required to hand over program deliverables, capabilities, and resources to the receiving operational organization. It ensures operational readiness and documents how resources are released and benefits are sustained after the program or phase concludes, directly matching the described scenario.
The communications management plan defines how information flows to stakeholders but has no function in directing resource release or operational handover.
The benefits management plan tracks benefit realization over time but does not contain the operational transfer procedures for resources and deliverables.
Concept tested: Program transition planning and resource release to operations
Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-program-management