nerdexam
PMI

PGMP · Question #232

Which of the following documents contain a list of all problems, unfavorable events, or situations that occurred so far in the program?

The correct answer is C. Program issue register. The program issue register is the official log of all problems, unfavorable events, and situations that have already occurred during program execution.

Program Life Cycle Management

Question

Which of the following documents contain a list of all problems, unfavorable events, or situations that occurred so far in the program?

Options

  • AProgram charter
  • BProgram risk register
  • CProgram issue register
  • DProgram scope statement

How the community answered

(25 responses)
  • B
    4% (1)
  • C
    92% (23)
  • D
    4% (1)

Why each option

The program issue register is the official log of all problems, unfavorable events, and situations that have already occurred during program execution.

AProgram charter

The program charter formally authorizes the program and names the program manager; it does not log problems or unfavorable events.

BProgram risk register

The program risk register tracks potential future risks and their response plans, not problems that have already occurred.

CProgram issue registerCorrect

The program issue register tracks all identified issues - problems and unfavorable events that have already materialized - along with their status, owners, and resolution actions, making it the definitive record of occurred problems throughout the program lifecycle.

DProgram scope statement

The program scope statement defines the work required to deliver the program's benefits and does not record problems or unfavorable events.

Concept tested: Program issue register purpose and contents

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-program-management

Topics

#Program Issue Register#Program Management Documents#Program Issues#Monitoring and Control

Community Discussion

No community discussion yet for this question.

Full PGMP Practice