Program Life Cycle Management
Question
Which of the following program process outputs includes causes of variances from the program management plan, corrective actions taken and their outcomes, risk mitigations, and other information of value to management and stakeholders of future programs?
Options
- ALessons learned
- BSupporting details
- CProgram management plan updates
- DAssumptions
Unlock PGMP to see the answer
You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Lessons learned#Program closure#Knowledge management#Organizational process assets