nerdexam
PMI

PGMP · Question #194

You are the program manager for a new software development program. One of the developers has been adding extra fields for information in the software that was not part of the original program scope.

The correct answer is D. Program scope change. This question addresses what it is called when work is added to a program outside the approved scope without going through the formal change control process.

Program Life Cycle Management

Question

You are the program manager for a new software development program. One of the developers has been adding extra fields for information in the software that was not part of the original program scope. While the fields are a good idea, the customer did not ask for the information and some time has been wasted on this work that was not in the program scope. This is an example of which one of the following terms?

Options

  • APreventive action
  • BCorrective action
  • CGold plating
  • DProgram scope change

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    14% (4)
  • C
    3% (1)
  • D
    76% (22)

Why each option

This question addresses what it is called when work is added to a program outside the approved scope without going through the formal change control process.

APreventive action

Preventive action refers to proactive steps taken to avoid future performance deviations, not to the unauthorized addition of work outside scope.

BCorrective action

Corrective action refers to steps taken to bring future performance back in alignment with the plan, not the introduction of unapproved out-of-scope work.

CGold plating

Gold plating describes adding extra quality or features beyond what was requested; the formal program management classification for work added outside the approved scope baseline is a scope change requiring change control.

DProgram scope changeCorrect

When a developer adds features that were not part of the approved program scope baseline, this constitutes an unauthorized program scope change - work was added without following the integrated change control process. Any addition of deliverables or work outside the approved scope must be formally evaluated and approved through change control before execution begins.

Concept tested: Unauthorized scope addition and change control

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-program-management

Topics

#Program Scope Management#Scope Change#Scope Baseline#Program Control

Community Discussion

No community discussion yet for this question.

Full PGMP Practice