Question

While your organization maintains a decision register after each meeting of the Portfolio Review Board, this register only notes decisions that are made when a component is added to the portfolio or if the Board terminates a component. If the component is terminated, the reason for the termination is not listed. Also if a proposed component is not approved, the reason is not listed. It is evident this register is lacking in its usefulness, which means it requires updating as it is:

Options

  • AIn the portfolio management plan
  • BA portfolio process asset
  • CAn organizational process asset
  • DPart of the governance model

Unlock PFMP to see the answer

You've previewed enough free PFMP questions. Unlock PFMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PFMP PracticeBrowse All PFMP Questions