nerdexam
PMIPMI

PFMP · Question #748

PFMP Question #748: Real Exam Question with Answer & Explanation

The correct answer is C: Weighted ranking and scoring techniques. See the full explanation below for the reasoning.

Question

Your organization has a defined portfolio management process that it has followed for three years. As the portfolio manager, you keep your various plans up to date, and because of numerous regulatory changes involving the telecom industry, it is time to review and update the risk management plan. You have several key stakeholders working with you as you realize the importance of this plan in maintaining a competitive advantage. One way you and your team are assessing the various risks that may impact the structure of the portfolio is to use:

Options

  • APortfolio component charts
  • BPortfolio reports
  • CWeighted ranking and scoring techniques
  • DRisk metrics

Community Discussion

No community discussion yet for this question.

Full PFMP PracticeBrowse All PFMP Questions