PFMP · Question #723

PFMP Question #723: Real Exam Question with Answer & Explanation

The correct answer is C: Prioritized for effective resource allocation. See the full explanation below for the reasoning.

Question

Although it has taken significant time, you and your team inventoried all the work under way in your new product development company. This list of components should be:

Options

  • AIncluded in the portfolio roadmap
  • BPart of the portfolio management plan
  • CPrioritized for effective resource allocation
  • DMaintained by the portfolio manager and continually updated