PFMP · Question #691
Your Portfolio Review Board is scheduled to meet in a week. Resources only are available to support one project, and detailed business cases have been prepared for two of them. Your company has a…
The correct answer is D. Project B but other qualitative items are not available. The correct answer is D: Project B, but other qualitative items are not available. In portfolio management, a complete recommendation to a Review Board requires both quantitative metrics (NPV, ROI, payback period, etc.) and qualitative factors (strategic alignment, stakeholder…
Question
Your Portfolio Review Board is scheduled to meet in a week. Resources only are available to support one project, and detailed business cases have been prepared for two of them. Your company has a policy of being risk adverse. Based on the following table, which project would you recommend to the Board, and what else would you mention to them?
Options
- AProject A and it has less risk associated with it
- BProject B and it has less risk associated with it
- CProject A as the benefits will be realized in a shorter time period
- DProject B but other qualitative items are not available
How the community answered
(38 responses)- A5% (2)
- B11% (4)
- C3% (1)
- D82% (31)
Explanation
The correct answer is D: Project B, but other qualitative items are not available. In portfolio management, a complete recommendation to a Review Board requires both quantitative metrics (NPV, ROI, payback period, etc.) and qualitative factors (strategic alignment, stakeholder impact, market conditions, etc.). While the table may show Project B as favorable based on quantitative data and risk profile, the portfolio manager has a professional obligation to inform the Board that qualitative data is absent. A risk-adverse company needs a full picture before committing resources. Simply pointing to numbers without flagging missing information would be an incomplete-and potentially misleading-recommendation. Answers A and B are incomplete because they only address risk without acknowledging missing qualitative data. Answer C is incorrect because a risk-adverse company should not prioritize speed of benefit realization over risk exposure.
Community Discussion
No community discussion yet for this question.