PFMP · Question #68

Which of the following are the output of "Develop Portfolio"? (Choose two.)

The correct answer is A. Portfolio Roadmap Updates D. Portfolio Management Plan Updates. The Develop Portfolio process produces updates to the portfolio roadmap and portfolio management plan as its key outputs.

Portfolio Performance Management

Question

Which of the following are the output of "Develop Portfolio"? (Choose two.)

Options

  • APortfolio Roadmap Updates
  • BPortfolio Process Assets
  • CPortfolio Reports
  • DPortfolio Management Plan Updates

How the community answered

(41 responses)
  • A
    90% (37)
  • B
    2% (1)
  • C
    7% (3)

Why each option

The Develop Portfolio process produces updates to the portfolio roadmap and portfolio management plan as its key outputs.

APortfolio Roadmap UpdatesCorrect

Portfolio Roadmap Updates are a direct output of Develop Portfolio because the process refines the time-phased view of portfolio components as they are evaluated and authorized.

BPortfolio Process Assets

Portfolio Process Assets are an input to, not an output of, Develop Portfolio; they provide templates and historical information used during the process.

CPortfolio Reports

Portfolio Reports are outputs of performance reporting and communication management processes, not of the Develop Portfolio process.

DPortfolio Management Plan UpdatesCorrect

Portfolio Management Plan Updates result from Develop Portfolio as decisions made during this process require revisions to governance, resource, and performance management plans documented within it.

Concept tested: Outputs of the Develop Portfolio process

Source: https://www.pmi.org/pmbok-guide-standards/foundational/portfolio-management

Topics

#Portfolio Processes#Develop Portfolio Process#Process Outputs#Portfolio Management Plan