PFMP · Question #21
You are managing portfolio information. Which inputs do you need? (Choose two.)
The correct answer is B. Portfolio process assets D. Portfolio reports. The 'Manage Portfolio Information' process requires existing process assets and current reports as inputs to guide how information is structured and communicated.
Question
You are managing portfolio information. Which inputs do you need? (Choose two.)
Options
- APortfolio strategic plan
- BPortfolio process assets
- CPortfolio roadmap
- DPortfolio reports
How the community answered
(25 responses)- A4% (1)
- B88% (22)
- C8% (2)
Why each option
The 'Manage Portfolio Information' process requires existing process assets and current reports as inputs to guide how information is structured and communicated.
The portfolio strategic plan is an input to strategic planning processes, not to the information management process.
Portfolio process assets include organizational policies, procedures, templates, and historical information that govern how portfolio information is managed and formatted.
The portfolio roadmap is a high-level timeline artifact used in planning processes, not a primary input to managing portfolio information.
Portfolio reports are existing outputs from prior reporting cycles that serve as inputs - they provide current state information needed when managing ongoing portfolio communication.
Concept tested: Inputs to Manage Portfolio Information process
Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management