Question

Assume you are creating a roadmap for your portfolio and will present it to key stakeholders and then to the Portfolio Review Board. You realize you will be adding additional detail to it, but you also believe its graphical format will be useful. In developing it, you decide to reference prioritization, dependencies, and organizational areas so you should consult the:

Options

  • AOrganization's strategic plan
  • BPortfolio strategic plan
  • CPortfolio charter
  • DPortfolio management plan