PFMP Question #615: Real Exam Question with Answer & Explanation
The correct answer is A: The project charter should be reviewed. See the full explanation below for the reasoning.
Question
Your organization conducted an OPM3 assessment focusing on its best practices in portfolio management and also on those that were needed. The OPM3 Certified Professional felt greater attention was needed managing strategic change. This means:
Options
- AThe project charter should be reviewed
- BThe strategic plan should be updated
- CBudget allocation can be handled more effectively
- DIt is easier to determine which components will require specialized resources