PFMP · Question #597

PFMP Question #597: Real Exam Question with Answer & Explanation

The correct answer is A: Measure the internal resource capacity and establish the external resources availability. See the full explanation below for the reasoning.

Question

A portfolio manager needs to continuously balance the need and requirements with the available resources to maintain a balanced portfolio and portfolio resources in order to optimize delivery. Capability and Capacity analysis is performed in 4 of the portfolio management processes and it serves a slightly different purpose in each and every one of them. When it relates to developing the charter, and in order to complete the portfolio structure, the capability and capacity analysis is used to

Options

  • AMeasure the internal resource capacity and establish the external resources availability
  • BMeasure internal and external resources capabilities and capacities
  • CMeasure the internal resource availability and establish the external resources capacity
  • DMeasure availability and capability of internal resources and forecast the use of external