nerdexam
PMIPMI

PFMP · Question #494

PFMP Question #494: Real Exam Question with Answer & Explanation

The correct answer is B: Portfolio Risks may be actively accepted in anticipation of high rewards, whereas, program and. See the full explanation below for the reasoning.

Strategic Alignment

Question

Risk management is an integral part of project, program and portfolio management and is invoked throughout the project, program and portfolio life cycle. Which of the following highlights the difference between portfolio risk and program or project risks?

Options

  • APortfolio risks focus on strategies, whereas program and project risks focus on implementation
  • BPortfolio Risks may be actively accepted in anticipation of high rewards, whereas, program and
  • CPortfolio risks are the aggregation of subsidiary programs and projects risks
  • DPortfolio risks can not be mitigated to other third parties, whereas program and project risks can

Topics

#Portfolio Risk Management#Strategic Risk#Risk Response#Risk Management Levels

Community Discussion

No community discussion yet for this question.

Full PFMP PracticeBrowse All PFMP Questions