nerdexam
PMI

PFMP · Question #494

Risk management is an integral part of project, program and portfolio management and is invoked throughout the project, program and portfolio life cycle. Which of the following highlights the differen

The correct answer is B. Portfolio Risks may be actively accepted in anticipation of high rewards, whereas, program and. The key distinction of portfolio risk is that it can be deliberately accepted in anticipation of high strategic rewards, reflecting the investment and value-optimization nature of portfolio management.

Strategic Alignment

Question

Risk management is an integral part of project, program and portfolio management and is invoked throughout the project, program and portfolio life cycle. Which of the following highlights the difference between portfolio risk and program or project risks?

Options

  • APortfolio risks focus on strategies, whereas program and project risks focus on implementation
  • BPortfolio Risks may be actively accepted in anticipation of high rewards, whereas, program and
  • CPortfolio risks are the aggregation of subsidiary programs and projects risks
  • DPortfolio risks can not be mitigated to other third parties, whereas program and project risks can

How the community answered

(16 responses)
  • B
    94% (15)
  • D
    6% (1)

Why each option

The key distinction of portfolio risk is that it can be deliberately accepted in anticipation of high strategic rewards, reflecting the investment and value-optimization nature of portfolio management.

APortfolio risks focus on strategies, whereas program and project risks focus on implementation

While portfolios are more strategy-focused, this is an oversimplification - programs and projects also address strategic implementation, and the real differentiator is the risk-reward acceptance posture, not merely strategy vs. implementation.

BPortfolio Risks may be actively accepted in anticipation of high rewards, whereas, program andCorrect

Portfolio management operates at the strategic level where risk tolerance is explicitly set and risks may be accepted when the expected return justifies the exposure - this is the concept of risk-reward optimization central to portfolio management. Program and project risks, by contrast, are generally managed to minimize impact on defined scope, schedule, and cost rather than accepted for strategic gain.

CPortfolio risks are the aggregation of subsidiary programs and projects risks

Portfolio risk is not simply the roll-up of subsidiary risks; it includes strategic, environmental, and organizational risks that exist independently at the portfolio level.

DPortfolio risks can not be mitigated to other third parties, whereas program and project risks can

Portfolio risks can be transferred or mitigated to third parties through contracts and insurance just as program and project risks can, so this is not a valid differentiator.

Concept tested: Portfolio-level risk acceptance vs. program and project risk management

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Risk Management#Strategic Risk#Risk Response#Risk Management Levels

Community Discussion

No community discussion yet for this question.

Full PFMP Practice