PFMP · Question #311
You have been assigned as the manager for a major transformation portfolio in your company. You have a new direction in sight and you need to work with the team to attain the end goal and achieve…
The correct answer is B. Portfolio Strategic Plan update, Portfolio Management Plan update, Portfolio Roadmap update. The 'Manage Strategic Change' process in portfolio management produces specific output documents when a strategic change has been finalized. The correct set of outputs includes the Portfolio Strategic Plan update (reflecting the new direction), Portfolio Management Plan update…
Question
You have been assigned as the manager for a major transformation portfolio in your company. You have a new direction in sight and you need to work with the team to attain the end goal and achieve the expected strategy. You have just finalized managing the strategic change and you are expected to present the following documents:
Options
- APortfolio Strategic Plan update, Portfolio Roadmap update, Portfolio Charter update, Portfolio
- BPortfolio Strategic Plan update, Portfolio Management Plan update, Portfolio Roadmap update,
- CPortfolio Strategic Plan update, Portfolio Roadmap update, Portfolio Charter update, Portfolio
- DPortfolio Strategic Plan update, Portfolio Roadmap update, Portfolio Charter update,
How the community answered
(31 responses)- A13% (4)
- B81% (25)
- C3% (1)
- D3% (1)
Explanation
The 'Manage Strategic Change' process in portfolio management produces specific output documents when a strategic change has been finalized. The correct set of outputs includes the Portfolio Strategic Plan update (reflecting the new direction), Portfolio Management Plan update (reflecting how the portfolio will be managed under the new strategy), and Portfolio Roadmap update (reflecting the updated timeline and sequencing). Answer B is correct because it includes the Portfolio Management Plan update, which is a key deliverable after finalizing strategic change. The other options either omit the Portfolio Management Plan update or include documents that are not standard outputs of this process, such as a Portfolio Charter update, which is typically updated at initiation or re-initiation rather than at the close of managing a strategic change.
Topics
Community Discussion
No community discussion yet for this question.