PFMP · Question #29

The above figure illustrates a pair-wise comparison of different portfolio components with one another. Which portfolio component has the least priority?

The correct answer is C. Project E. In a pair-wise comparison matrix, the component with the fewest wins across all comparisons receives the lowest priority score.

Portfolio Strategic Alignment

Question

The above figure illustrates a pair-wise comparison of different portfolio components with one another. Which portfolio component has the least priority?

Exhibit

PFMP question #29 exhibit

Options

  • AProject A
  • BProject D
  • CProject E
  • DProject F

How the community answered

(26 responses)
  • A
    12% (3)
  • B
    4% (1)
  • C
    81% (21)
  • D
    4% (1)

Why each option

In a pair-wise comparison matrix, the component with the fewest wins across all comparisons receives the lowest priority score.

AProject A

Project A scored more wins than Project E in the pair-wise comparison matrix shown in the figure.

BProject D

Project D accumulated more comparison wins than Project E, placing it higher in the priority ranking.

CProject ECorrect

Pair-wise comparison scores each component against every other component one at a time, and totals the wins for each. Project E accumulated the fewest wins across all comparisons in the referenced figure, yielding the lowest relative priority among all components.

DProject F

Project F received a higher total score than Project E in the pair-wise comparison, giving it a higher priority.

Concept tested: Pair-wise comparison prioritization analysis

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Prioritization#Pairwise Comparison#Strategic Alignment#Decision Making