PFMP Question #309: Real Exam Question with Answer & Explanation

The correct answer is D: Inventory of Work. See the full explanation below for the reasoning.

Portfolio Strategic Alignment

Question

As part of the annual planning, PMO has started to group initiatives managed under each portfolio in the organization. The collected list will be used in developing the new Portfolio Strategic Plan. What is this collected list called?

Options

  • APortfolio
  • BPortfolio Component Inventory
  • CPortfolio Process Assets (PPAs)
  • DInventory of Work

Topics

#Portfolio Management#Portfolio Components#Strategic Planning#Portfolio Planning