During the portfolio lifecycle, you will be using the roadmap a lot and you be using it to report progress to different stakeholders. When it comes to portfolio roadmap, which of the following…

The correct answer is B. Roadmap includes internal and external dependencies to other organizational areas. The portfolio roadmap is a high-level strategic document used to communicate portfolio direction and is specifically designed to capture both internal and external dependencies to other organizational areas, making Option B correct. Option A is false – roadmaps are living…

Strategic Alignment

Question

During the portfolio lifecycle, you will be using the roadmap a lot and you be using it to report progress to different stakeholders. When it comes to portfolio roadmap, which of the following options is true?

Options

  • ARoadmap are rarely updated, in contrast to the portfolio charter which gets frequently updated
  • BRoadmap includes internal and external dependencies to other organizational areas
  • CRoadmap is defined after the planning of all components is finished
  • DRoadmaps incorporate all components and shows a graphical representation of the portfolio

How the community answered

(27 responses)
  • B
    89% (24)
  • C
    7% (2)
  • D
    4% (1)

Explanation

The portfolio roadmap is a high-level strategic document used to communicate portfolio direction and is specifically designed to capture both internal and external dependencies to other organizational areas, making Option B correct. Option A is false – roadmaps are living documents that are updated regularly as the portfolio evolves, while the charter is relatively more stable. Option C is false – the roadmap is not defined only after all component planning is finished; it is developed iteratively throughout the portfolio lifecycle. Option D is partially misleading – while the roadmap shows components graphically, it does not necessarily incorporate ALL components at all times; it reflects active, planned, and pipeline components relevant to the strategic horizon.

Topics

#Portfolio Roadmap#Dependencies Management#Portfolio Planning

Community Discussion