PFMP · Question #279

You have been assigned as the manager for a major transformation portfolio in your company. You have a new direction in sight and you need to work with the team to attain the end goal and achieve…

The correct answer is A. Portfolio, Portfolio Strategic Plan. The Develop Portfolio Strategic Plan process produces two key outputs: the Portfolio itself and the Portfolio Strategic Plan.

Strategic Alignment

Question

You have been assigned as the manager for a major transformation portfolio in your company. You have a new direction in sight and you need to work with the team to attain the end goal and achieve the expected strategy. For this you start by developing the strategic plan. What output do you expect from this process?

Options

  • APortfolio, Portfolio Strategic Plan
  • BPortfolio, Portfolio Strategic Plan, Portfolio Reports
  • CPortfolio, Portfolio Strategic Plan, Enterprise Environmental Factors updates
  • DPortfolio Process Assets updates, Inventory Of Work, Portfolio, Portfolio Strategic Plan

How the community answered

(60 responses)
  • A
    95% (57)
  • C
    2% (1)
  • D
    3% (2)

Why each option

The Develop Portfolio Strategic Plan process produces two key outputs: the Portfolio itself and the Portfolio Strategic Plan.

APortfolio, Portfolio Strategic PlanCorrect

According to the PMI Standard for Portfolio Management, the Develop Portfolio Strategic Plan process has two primary outputs: the Portfolio (the formal collection of components) and the Portfolio Strategic Plan (the document defining the portfolio's direction, goals, and alignment to organizational strategy). Other documents such as Portfolio Reports and Enterprise Environmental Factor updates are outputs of different processes and are not produced by this specific process.

BPortfolio, Portfolio Strategic Plan, Portfolio Reports

Portfolio Reports are an output of the Provide Portfolio Oversight process, not the Develop Portfolio Strategic Plan process.

CPortfolio, Portfolio Strategic Plan, Enterprise Environmental Factors updates

Enterprise Environmental Factors are inputs to processes, not outputs; they are not produced by the Develop Portfolio Strategic Plan process.

DPortfolio Process Assets updates, Inventory Of Work, Portfolio, Portfolio Strategic Plan

Portfolio Process Assets updates and Inventory of Work are associated with other portfolio management processes, not with developing the strategic plan.

Concept tested: Outputs of Develop Portfolio Strategic Plan process

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Strategic Plan#Portfolio Outputs#Strategic Planning#Portfolio Management Processes