Along your portfolio lifecycle, you have been conducting multiple review meetings to ensure continuation from one phase to another and to ensure the alignment and value delivery, in addition to…

The correct answer is A. Portfolio Management Plan updates. Changes to the portfolio governance approach resulting from review meetings are captured as updates to the Portfolio Management Plan, which is the document that contains the governance model.

Portfolio Governance

Question

Along your portfolio lifecycle, you have been conducting multiple review meetings to ensure continuation from one phase to another and to ensure the alignment and value delivery, in addition to communicating decisions and valuable information to the related stakeholders. Changes to the approach of portfolio governance may be a result of review meetings. Which of the following options include updates to the governance model?

Options

  • APortfolio Management Plan updates
  • BPortfolio Process Assets updates
  • CPortfolio Reports
  • DPortfolio Strategic Plan updates

How the community answered

(16 responses)
  • A
    94% (15)
  • C
    6% (1)

Why each option

Changes to the portfolio governance approach resulting from review meetings are captured as updates to the Portfolio Management Plan, which is the document that contains the governance model.

APortfolio Management Plan updatesCorrect

The Portfolio Management Plan is the document that defines the governance model, including how decisions are made, how performance is reviewed, and how the portfolio is managed. When review meetings result in changes to the governance approach, those changes are reflected as updates to the Portfolio Management Plan. This ensures that governance changes are formally documented and integrated into ongoing portfolio management activities.

BPortfolio Process Assets updates

Portfolio Process Assets updates capture historical information and lessons learned, not formal changes to the governance model itself.

CPortfolio Reports

Portfolio Reports communicate status and performance data to stakeholders but do not contain or update governance model definitions.

DPortfolio Strategic Plan updates

Portfolio Strategic Plan updates reflect changes in strategic direction and objectives, not changes to the governance approach or model.

Concept tested: Portfolio Management Plan updates for governance changes

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Governance#Portfolio Management Plan#Portfolio Lifecycle#Review Meetings

Community Discussion

No community discussion yet for this question.

Full PFMP Practice