The correct answer is B: Indicates the threshold of the organization toward the effects of risk on the portfolio. See the full explanation below for the reasoning.

Portfolio Risk Management

Question

What is the purpose of identifying risk tolerance in portfolio management?

Options

  • AProvides a technique for mapping the probability and impact of each risk occurrence
  • BIndicates the threshold of the organization toward the effects of risk on the portfolio
  • CDocuments the probability impact of total component risk on the overall portfolio
  • DDefines the acceptable cost variance (CV) assigned to each portfolio component

Topics

#Risk Tolerance#Portfolio Risk Management#Organizational Risk Thresholds