Which of the following are the key activities with the "Define Portfolio" process?

The correct answer is A. Evaluating portfolio components with a ranking and scoring model comprising weighted key C. Categorizing portfolio components to which a common set of decision filters and criteria may be. The 'Define Portfolio' process focuses on identifying and grouping portfolio components into categories and evaluating them for selection. Key activities include: evaluating portfolio components using ranking and scoring models with weighted criteria (A), and categorizing…

Strategic Alignment

Question

Which of the following are the key activities with the "Define Portfolio" process?

Options

  • AEvaluating portfolio components with a ranking and scoring model comprising weighted key
  • BEvaluating and determining performance and expected value and benefits (financial and non-
  • CCategorizing portfolio components to which a common set of decision filters and criteria may be
  • DDetermining resource (human, assets, and technology) capability, resource capacity available,

How the community answered

(29 responses)
  • A
    86% (25)
  • B
    10% (3)
  • D
    3% (1)

Explanation

The 'Define Portfolio' process focuses on identifying and grouping portfolio components into categories and evaluating them for selection. Key activities include: evaluating portfolio components using ranking and scoring models with weighted criteria (A), and categorizing portfolio components so that common decision filters and criteria can be applied (C). Option B (evaluating performance and expected value) aligns more with 'Optimize Portfolio,' and option D (determining resource capacity) aligns with 'Manage Supply and Demand.'

Topics

#Portfolio Definition#Portfolio Components#Categorization#Portfolio Evaluation