- Question #51Documentation
Which standards are generally established by private-sector bodies and are available for use by any person or Organization, private or government?
voluntary standardsconsensus standardsprivate-sector standardsregulatory framework - Question #52Inspection Procedures
The HATE adhesion tester uses
HATE adhesion testeradhesion testinghydraulic pistontest equipment - Question #53Surface Preparation
In which type of concrete are laitance commonly encountered?
laitancepoured concretewet cast concreteconcrete surface types - Question #54Safety
Generally for safety considerations, waterjetting hose connections use
waterjetting safetywhip-lock devicehose connectionshigh-pressure water - Question #55Coating Application
The number of air turns in an enclosure can be affected by all of these EXCEPT
air turnsenclosure ventilationdehumidification equipmentenvironmental control - Question #56Surface Preparation
Pre-cleaning of work pieces will NOT remove
pre-cleaningmill scalesurface contaminantsabrasive blasting - Question #57Surface Preparation
Which concrete smoothing technique involves scrubbing a mixture of cement mortar over the concrete surface using ai cement sack, gunny sack, or sponge rubber float?
sackingcement mortarconcrete smoothingsurface preparation techniques - Question #58Corrosion Control Methods
Which type of pipelines collect the gas from the transmission system so utility companies can distribute the gas to end users?
distribution pipelinesgas pipelinestransmission systempipeline types - Question #59Safety
You should bulk store coatings containing isocyanates
isocyanatescoating storageventilationhazardous materials - Question #60Corrosion Control Methods
Which product, is used in conjunction with other coatings such as FBE when the lines run through wetlands or a body of water?
concrete coatingFBEpipeline protectionwetlands coating - Question #61Inspection Procedures
Inspectors perform tests on linings that they may not perform on exterior coatings because
lining vs coatinglining inspectioncontainer protectioninspector rationale - Question #62Curing Mechanisms
The solvent sensitivity/solvent wipe test (ASTM D4752) is used to determine the cure of
ASTM D4752solvent wipe testinorganic zinc curecure testing - Question #63Coating Application
Which product, when closely inspected has a green or red layer of fusion bonded epoxy (FBE) that is visible directly on the steel?
3-layer polyethylenefusion bonded epoxypipeline coatingscoating identification - Question #64Coating Application
Cold-applied tape
cold-applied tapepolyethylene backingbutyl adhesivepipeline coatings - Question #65Surface Preparation
Examples of non-ferrous metals include Select All that Apply:
non-ferrous metalsaluminumcoppersubstrate classification - Question #66Safety
Antifouling coatings are regulated by international treaties.
antifouling coatingsinternational treatiesmarine coatingsregulatory compliance - Question #67Coating Failures
A failure caused by applying a coating too thinly is known as
pinholesthin film applicationapplication defectscoating failures - Question #69Safety
You are the NACE Coating Inspector on a tank lining project and are asked to perform a high voltage holiday test after the coating applicators have completed their final repairs. A...
confined space entrysolvent vapor hazardholiday testingemergency response - Question #70Safety
You are working as an inspector in a galvanizing plant for the first time. What are some of the hazards you need to be aware of:
galvanizing hazardschemical exposureacid splashworkplace safety - Question #71Inspection Procedures
You are working as the only in-house NACE Level 2 Inspector in a shop setting when an independent 3rd party NACE Level 3 Inspector, representing the owner, presents you with a copy...
non-conformance reportNCR protocolinspector conflict resolutionSSPC SP10 - Question #72Documentation
An Inspection and Test Plan is required when:
inspection and test planITP requirementsowner specificationproject documentation - Question #74Inspection Procedures
Coating Surveys are legally required:
coating surveysmarine vesselsoffshore platformslegal requirements - Question #75Inspection Procedures
Individuals conducting Coating Surveys should:
coating survey personnelinspector qualificationsindustry experienceNACE certification - Question #76Inspection Procedures
The cost of qualified Coating Inspection is normally offset by:
inspection economicslife cycle costscoating inspection valuecost justification - Question #77Inspection Procedures
You are a NACE Level 2 Coating Inspector who has just arrived on a job in progress where there is no Inspection and Test Plan (ITP). The first morning you arrive the job is behind...
dry film thicknessITP absenceindustry standardsinspector decision-making - Question #78Inspection Procedures
When conducting inspections the Inspector should follow which standards:
inspection standardsNACE standardsISO standardsspecified standards compliance - Question #79Inspection Procedures
You are the NACE Level 2 Coating Inspector where SSPC PA 2 has been specified with an additional requirement that no individual gauge reading shall be below a certain value. As thi...
SSPC PA 2film thickness requirementsspecification clarificationadditional requirements - Question #80Curing Mechanisms
When performing testing in accordance with ASTM D 2583 the inspector may observe:
ASTM D2583Barcol hardnesscold flowcreep - Question #81Surface Preparation
When NACE/SSPC WJ 1 is referenced; what type of equipment would the Inspector expect to see on the job:
NACE/SSPC WJ1water jettingsurface preparation standardsequipment identification - Question #82Surface Preparation
NACE/SSPC Water Jetting standards are directly equivalent to ISO Abrasive Blast Standards:
water jetting standardsISO abrasive blast standardsNACE/SSPC standardsstandards equivalency - Question #83Documentation
NACE Standards include:
NACE standardsStandard PracticesMaterial Requirements - Question #84Inspection Procedures
You are the new NACE Level 2 Inspector on a job which had been very problematic. The previous Inspector was fired duo to personality conflicts with the Contractor's supervisor. Upo...
professional conductconflict resolutioninspector ethicssite relationships - Question #85Inspection Procedures
When working with someone who is very concerned about Stability and maintaining adherence to the status-quo, the Inspector should try to:
communication styleschange managementinspector relationships - Question #86Inspection Procedures
You have just your NACE CIP Level 2 certification when you are asked to supervise a team of uncertified field pipeline inspectors. Your FIRST preferred course of action is to:
NACE certificationscope of workprofessional ethicsinspector responsibilities - Question #87Inspection Procedures
NACE Level 2 Inspectors have been authorized to perform:
NACE Level 2certification scopeNDTinspection types - Question #88Inspection Procedures
You can use magnifiers to examine all of the following EXCEPT
magnifiersvisual inspection toolssurface profilesurface cleanliness - Question #89Surface Preparation
Steel shot grit contaminated with oil or grease used in a cetrifugal blast cleaning should be
abrasive contaminationcentrifugal blast cleaningabrasive disposaloil contamination - Question #90Coating Application
On pipelines, which coating is identifiable by its distinct colors, usually light blue, green, or grey?
pipeline coatingsliquid epoxiescoating identificationcolor coding - Question #91Inspection Procedures
The coating applicator has ignored a enface preparation hold point and applied coating over the surface without a sign off from you as the inspector. Your FIRST preferred course of...
hold pointsnon-conformanceinspector authoritysurface preparation - Question #92Documentation
In the event of a conflict between the Product Data Sheet and the Specification:
specificationsproduct data sheetdocument hierarchy - Question #93Corrosion Control Methods
From a corrosion perspective, the main difference between Ferrous and Non-Ferrous Metals is:
ferrous metalsnon-ferrous metalsiron contentcorrosion - Question #94Coating Application
You are the NACY Coating Inspector on a tank lining project where desiccant dehumidification is being used. Since the first shift of abrasive blasting your readings have indicated...
relative humiditydehumidification equipmentenvironmental monitoringcoating application conditions - Question #95Inspection Procedures
When environmental enclosures are being used an inspector needs to be concerned about:
environmental enclosureslightingair changesstructural integrity - Question #96Inspection Procedures
It is always possible to see moisture on a steel substrate:
moisture detectionsteel substratesurface inspectioncondensation - Question #97Coating Failures
When observing design defects the NACE Inspector should:
design defectsdocumentationinspector rolecoating design - Question #98Surface Preparation
When observing fabrication defects the NACE Inspector should:
fabrication defectsspecification complianceinspector rolesurface remediation - Question #99Surface Preparation
WJ-1 is always performed using UHWJ at pressures above 210 MPa (30,000 PSI)
WJ-1UHPWJwater jettingsurface preparation pressure - Question #100Surface Preparation
Centrifugal blast cleaning requires:
centrifugal blast cleaningblast wheelsabrasive blastingsurface preparation equipment