NACE-CIP2-001 Exam Questions
98 real NACE-CIP2-001 exam questions with expert-verified answers and explanations. Page 2 of 2.
- Question #51
Which standards are generally established by private-sector bodies and are available for use by any person or Organization, private or government?
- Question #52
The HATE adhesion tester uses
- Question #53
In which type of concrete are laitance commonly encountered?
- Question #54
Generally for safety considerations, waterjetting hose connections use
- Question #55
The number of air turns in an enclosure can be affected by all of these EXCEPT
- Question #56
Pre-cleaning of work pieces will NOT remove
- Question #57
Which concrete smoothing technique involves scrubbing a mixture of cement mortar over the concrete surface using ai cement sack, gunny sack, or sponge rubber float?
- Question #58
Which type of pipelines collect the gas from the transmission system so utility companies can distribute the gas to end users?
- Question #59
You should bulk store coatings containing isocyanates
- Question #60
Which product, is used in conjunction with other coatings such as FBE when the lines run through wetlands or a body of water?
- Question #61
Inspectors perform tests on linings that they may not perform on exterior coatings because
- Question #62
The solvent sensitivity/solvent wipe test (ASTM D4752) is used to determine the cure of
- Question #63
Which product, when closely inspected has a green or red layer of fusion bonded epoxy (FBE) that is visible directly on the steel?
- Question #64
Cold-applied tape
- Question #65
Examples of non-ferrous metals include Select All that Apply:
- Question #66
Antifouling coatings are regulated by international treaties.
- Question #67
A failure caused by applying a coating too thinly is known as
- Question #69
You are the NACE Coating Inspector on a tank lining project and are asked to perform a high voltage holiday test after the coating applicators have completed their final repairs. A...
- Question #70
You are working as an inspector in a galvanizing plant for the first time. What are some of the hazards you need to be aware of:
- Question #71
You are working as the only in-house NACE Level 2 Inspector in a shop setting when an independent 3rd party NACE Level 3 Inspector, representing the owner, presents you with a copy...
- Question #72
An Inspection and Test Plan is required when:
- Question #74
Coating Surveys are legally required:
- Question #75
Individuals conducting Coating Surveys should:
- Question #76
The cost of qualified Coating Inspection is normally offset by:
- Question #77
You are a NACE Level 2 Coating Inspector who has just arrived on a job in progress where there is no Inspection and Test Plan (ITP). The first morning you arrive the job is behind...
- Question #78
When conducting inspections the Inspector should follow which standards:
- Question #79
You are the NACE Level 2 Coating Inspector where SSPC PA 2 has been specified with an additional requirement that no individual gauge reading shall be below a certain value. As thi...
- Question #80
When performing testing in accordance with ASTM D 2583 the inspector may observe:
- Question #81
When NACE/SSPC WJ 1 is referenced; what type of equipment would the Inspector expect to see on the job:
- Question #82
NACE/SSPC Water Jetting standards are directly equivalent to ISO Abrasive Blast Standards:
- Question #83
NACE Standards include:
- Question #84
You are the new NACE Level 2 Inspector on a job which had been very problematic. The previous Inspector was fired duo to personality conflicts with the Contractor's supervisor. Upo...
- Question #85
When working with someone who is very concerned about Stability and maintaining adherence to the status-quo, the Inspector should try to:
- Question #86
You have just your NACE CIP Level 2 certification when you are asked to supervise a team of uncertified field pipeline inspectors. Your FIRST preferred course of action is to:
- Question #87
NACE Level 2 Inspectors have been authorized to perform:
- Question #88
You can use magnifiers to examine all of the following EXCEPT
- Question #89
Steel shot grit contaminated with oil or grease used in a cetrifugal blast cleaning should be
- Question #90
On pipelines, which coating is identifiable by its distinct colors, usually light blue, green, or grey?
- Question #91
The coating applicator has ignored a enface preparation hold point and applied coating over the surface without a sign off from you as the inspector. Your FIRST preferred course of...
- Question #92
In the event of a conflict between the Product Data Sheet and the Specification:
- Question #93
From a corrosion perspective, the main difference between Ferrous and Non-Ferrous Metals is:
- Question #94
You are the NACY Coating Inspector on a tank lining project where desiccant dehumidification is being used. Since the first shift of abrasive blasting your readings have indicated...
- Question #95
When environmental enclosures are being used an inspector needs to be concerned about:
- Question #96
It is always possible to see moisture on a steel substrate:
- Question #97
When observing design defects the NACE Inspector should:
- Question #98
When observing fabrication defects the NACE Inspector should:
- Question #99
WJ-1 is always performed using UHWJ at pressures above 210 MPa (30,000 PSI)
- Question #100
Centrifugal blast cleaning requires: