Microsoft
MB6-700 · Question #65
You attach an invoice format to the project contract. Which item is controlled by the invoice format setting?
The correct answer is C. Invoice summarization. See the full explanation below for the reasoning.
Question
You attach an invoice format to the project contract. Which item is controlled by the invoice format setting?
Options
- AInvoice output destination
- BInvoice currency
- CInvoice summarization
- DInvoice orientation
How the community answered
(29 responses)- A7% (2)
- B10% (3)
- C79% (23)
- D3% (1)
Community Discussion