MB6-700 · Question #62

MB6-700 Question #62: Real Exam Question with Answer & Explanation

The correct answer is D. Worker. See the full explanation below for the reasoning.

Question

You assign resources to a project quotation with a work breakdown structure. Competencies are used to determine which resources are appropriate for assignment. On which entity are competencies set?

Options

  • ARole
  • BPosition
  • CUser
  • DWorker