nerdexam
Microsoft

MB6-700 · Question #59

MB6-700 Question #59: Real Exam Question with Answer & Explanation

The correct answer is C. Reallocating a project budget from another project. See the full explanation below for the reasoning.

Question

Which task is allowed after a budget is approved?

Options

  • ACreating an additional project budget for the project
  • BCreating a general ledger budget for a new subproject
  • CReallocating a project budget from another project
  • DBuilding a forecast model from the project budget

Community Discussion

No community discussion yet for this question.

Full MB6-700 Practice