Microsoft
MB6-700 · Question #59
MB6-700 Question #59: Real Exam Question with Answer & Explanation
The correct answer is C. Reallocating a project budget from another project. See the full explanation below for the reasoning.
Question
Which task is allowed after a budget is approved?
Options
- ACreating an additional project budget for the project
- BCreating a general ledger budget for a new subproject
- CReallocating a project budget from another project
- DBuilding a forecast model from the project budget
Community Discussion
No community discussion yet for this question.