MB6-700 · Question #53

You work with a fixed-price project. To which process do the completed contract and completed percentage assessment principles relate?

The correct answer is A. Posting revenue. See the full explanation below for the reasoning.

Question

You work with a fixed-price project. To which process do the completed contract and completed percentage assessment principles relate?

Options

  • APosting revenue
  • BTransferring costs from balance sheet to profit and loss accounts
  • CPosting costs
  • DAccumulating costs in balance sheet accounts

How the community answered

(52 responses)
  • A
    85% (44)
  • B
    8% (4)
  • C
    4% (2)
  • D
    4% (2)