The correct answer is B. It can show availability of a resource.. See the full explanation below for the reasoning.
Question
What can the Resource assignment analysis report do that the Resource assignments report cannot do?
Options
- AIt can show how many hours a resource is assigned to a project.
- BIt can show availability of a resource.
- CIt can be filtered to include certain commitment types.
- DIt can be filtered to include a specified date range.