What can the Resource assignment analysis report do that the Resource assignments report cannot do?

The correct answer is B. It can show availability of a resource. See the full explanation below for the reasoning.

Question

What can the Resource assignment analysis report do that the Resource assignments report cannot do?

Options

  • AIt can show how many hours a resource is assigned to a project.
  • BIt can show availability of a resource.
  • CIt can be filtered to include certain commitment types.
  • DIt can be filtered to include a specified date range.

How the community answered

(48 responses)
  • A
    15% (7)
  • B
    71% (34)
  • C
    4% (2)
  • D
    10% (5)