MB6-700 · Question #33

You are responsible for a customer's fixed-price project. The customer requests that you provide additional spare parts. The purchase of these spare parts falls outside the scope of the project. You…

The correct answer is B. Create the sales order by using a subproject of the type time and material. See the full explanation below for the reasoning.

Question

You are responsible for a customer's fixed-price project. The customer requests that you provide additional spare parts. The purchase of these spare parts falls outside the scope of the project. You need to ensure that the customer is charged for the spare parts. How should you create the sales order so that the customer is invoiced for the spare parts?

Options

  • ACreate the sales order by using a subproject of the type cost.
  • BCreate the sales order by using a subproject of the type time and material.
  • CThe sales order cannot be created because this is a fixed-price project.
  • DCreate the sales order from the fixed-price project and ensure that the line property for the

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    73% (16)
  • C
    14% (3)
  • D
    9% (2)