You analyze the progress of a project. Which two groups of parameters should you configure prior to using the Hour utilization form? (Each correct answer presents part of the solution. Choose two.)
The correct answer is C. Definition of billable rate D. Definition of efficiency rate. See the full explanation below for the reasoning.
Question
You analyze the progress of a project. Which two groups of parameters should you configure prior to using the Hour utilization form? (Each correct answer presents part of the solution. Choose two.)
Options
- ABudget overrun default
- BBudget control interval
- CDefinition of billable rate
- DDefinition of efficiency rate
How the community answered
(43 responses)- A7% (3)
- B14% (6)
- C79% (34)