Which three actions are part of the basic setup for indirect costs? (Each correct answer presents part of the solution. Choose three.)
The correct answer is A. Creating an indirect component group B. Setting up revenue accounts in the Project categories form D. Defining an indirect component category. See the full explanation below for the reasoning.
Question
Which three actions are part of the basic setup for indirect costs? (Each correct answer presents part of the solution. Choose three.)
Options
- ACreating an indirect component group
- BSetting up revenue accounts in the Project categories form
- CCreating an indirect component
- DDefining an indirect component category
- ESetting up the cost accounts in the Project categories form
How the community answered
(36 responses)- A72% (26)
- C19% (7)
- E8% (3)