Microsoft
MB6-700 · Question #19
You need to set up a pay when paid (PWP) term for a project. Which project type should you choose?
The correct answer is A. Time and material. See the full explanation below for the reasoning.
Question
You need to set up a pay when paid (PWP) term for a project. Which project type should you choose?
Options
- ATime and material
- BInternal
- CCost
- DFixed-price
How the community answered
(22 responses)- A82% (18)
- B5% (1)
- C9% (2)
- D5% (1)
Community Discussion