You create a project contract. You need to include indirect costs. Which billing rule should you select?
The correct answer is C. Time and material. See the full explanation below for the reasoning.
Question
You create a project contract. You need to include indirect costs. Which billing rule should you select?
Options
- AProgress
- BUnit of delivery
- CTime and material
- DMilestone
How the community answered
(20 responses)- A5% (1)
- B10% (2)
- C70% (14)
- D15% (3)