You need to illustrate the dimensions of the project management diamond. Which dimension should you place at the center of the diamond?
The correct answer is D. expectations. See the full explanation below for the reasoning.
Question
You need to illustrate the dimensions of the project management diamond. Which dimension should you place at the center of the diamond?
Options
- Aquality
- Bcost
- Ctime
- Dexpectations
- Escope
How the community answered
(37 responses)- A5% (2)
- B3% (1)
- C3% (1)
- D76% (28)
- E14% (5)