You are a project manager. You use the classic triple constraint model. If one constraint is changed, what happens to the other constraints?
The correct answer is C. At least one of the other constraints must also change. See the full explanation below for the reasoning.
Question
You are a project manager. You use the classic triple constraint model. If one constraint is changed, what happens to the other constraints?
Options
- AThe project's quality constraint will change.
- BThe project's expectations constraint will change.
- CAt least one of the other constraints must also change.
- DThe customer's benefits constraint will change.
How the community answered
(54 responses)- A6% (3)
- B17% (9)
- C70% (38)
- D7% (4)