nerdexam
Microsoft

MB5-858 · Question #74

You are a project manager, and you use Microsoft Dynamics Sure Step Methodology to manage projects. You need to ensure that quality assurance is part of a project that you are managing. Which item…

The correct answer is C. quality assurance reviews with stakeholders, scheduled early and often across all project phases. See the full explanation below for the reasoning.

Question

You are a project manager, and you use Microsoft Dynamics Sure Step Methodology to manage projects. You need to ensure that quality assurance is part of a project that you are managing. Which item should you include as part of the project?

Options

  • Aa comprehensive review with the project stakeholders at the end of the project
  • Ba review process done at the beginning and checked off at the end of the project with the project stakeholders
  • Cquality assurance reviews with stakeholders, scheduled early and often across all project phases
  • Da comprehensive review process performed if problems occur during the project or at a stakeholder's request

How the community answered

(35 responses)
  • A
    9% (3)
  • B
    3% (1)
  • C
    83% (29)
  • D
    6% (2)

Community Discussion

No community discussion yet for this question.

Full MB5-858 Practice